Innovative high capital cost projects commonly overrun in costs and time but only the ferries in Scotland can be exploited by the ruthless hypocrites

It’s been ages, two days, since the last ferry fiasco story, likely to affect the voting behaviour of almost no voters of course but you can be sure there will be a big one on Wednesday night, maybe even on the day of the vote? Look and laugh. What will you not hear? Well-known examples 1. Hinkley Point C (UK nuclear power) New-generation nuclear plant Costs rose dramatically from initial estimates Years behind schedule Classic case of combining regulatory complexity with first-of-type engineering 2. Crossrail (London rail project) Highly innovative urban rail integration Opened several years late and billions over … Continue reading Innovative high capital cost projects commonly overrun in costs and time but only the ferries in Scotland can be exploited by the ruthless hypocrites